Please be advised that effective Wednesday, October 2, 2019, Alberta Transportation will be conducting an urgent concrete deck patching on the Highway 49 bridge South of Guy.

This work will be ongoing till approximately October 18, 2019. They understand that this is a crucial time for farmers and have provided an accommodation schedule twice per day for those that need to use this location.

Please see below for the accommodation times. Note that these times may change according to the weather.

*Wednesday October 2:  8am-10am accommodation and then concrete pour
*Thursday October 3: 6pm-8pm
*Friday October 4 through Tuesday October 8: 8am-10am and 6pm-8pm accommodation
*Wednesday October 9: no accommodation
*Thursday October 10 through Friday October 18: 8am-10am and 6pm-8pm accomodation

Please check 511 Alberta for any updates at: https://511.alberta.ca

Regular heavy truck traffic can get through 24/7, this includes hauling. The schedule above is for the wider equipment (combines). If you have any questions regarding this matter please contact Alberta Transportation. Thank you.